An asset-light developer does not buy the land it builds on. It partners with the landowner through a joint development, a revenue share or a development-management contract, and contributes design, approvals, construction, marketing, sales and sometimes operations. The developer needs less capital and carries less land risk. The landowner keeps a stake in the project's value, but also shares its risks. Under RERA, a landowner with a share of the units or sales may be treated as a promoter with duties to buyers. Maharashtra's regulator treats such landowners as promoters as a rule; elsewhere, the Kerala High Court has looked at the landowner's actual role.
An asset-light developer builds on land it does not own. Instead of paying for the land up front, it partners with the landowner, and both are paid out of the project. This guide sets out the three common structures, who uses them, and what they mean for you as the owner, including your position under RERA.
Three ways to be asset-light
| Model | The landowner | The developer | Who sells |
|---|---|---|---|
| Joint development (area share) | Contributes land, receives a share of the built units or plots | Builds and sells its share | Each side sells its own share, or the developer sells all |
| Revenue share | Contributes land, receives a percentage of sales receipts | Builds and sells everything | The developer |
| Development management (DM) | Owns the project and funds it | Runs design, approvals, construction, marketing and sales on the owner’s behalf, under a contract | The developer, on the owner’s behalf |
Many deals mix these. Read our guides on joint development agreements and revenue-share agreements for how each works in detail.
Why developers choose it
Arvind SmartSpaces’ 2023-24 annual report gives reasons for its joint developments that apply to the model generally:1
- Less capital. It can expand without a large capital outlay, because it does not pay for the land up front.
- Less land risk. If approvals take years, the developer has not paid for land that sits idle.
- Faster timelines. Land that comes through a joint development is usually ready to develop.
Not every developer is moving one way. The same report says Arvind SmartSpaces plans to increase the share of projects on land it owns outright, relative to joint development agreements.1
Who uses it
Large developers, including listed ones, use these structures. A few examples from public sources:
- Godrej Properties said in a regulatory filing in February 2026 that it had signed a joint development agreement with a landowner for a project in the Mumbai region.2
- Arvind SmartSpaces’ 2023-24 annual report describes a large township taken up on a joint development model, and a smaller township under a development-management agreement with a subsidiary of Arvind Ltd.3
- Puravankara signed a joint development agreement in Bengaluru in March 2026, and said it was expanding through asset-light partnerships.4
- Della Townships describes itself as asset-light and describes an end-to-end service it calls CDDMO: conceptualising, design, development, marketing, sales and operations (company-stated, as of 27 November 2026).5 DEVELOPER-STATED When we searched MahaRERA’s register by project name on 27 November 2026, none of the township collaborations Della Townships lists in Maharashtra appeared.6 We have not searched other states’ registers. We name none of the collaborations.
The list is illustrative, not a ranking. Being asset-light says nothing on its own about how well a developer delivers. Judge each one on its record.
What it means for the landowner
The upside. You keep a stake in what the land becomes, rather than selling at today’s price. Whether that ends up worth more than a sale depends on the terms and on the project being approved, built and sold.
The risks.
- Delay. Your land is committed for the life of the project. If approvals or sales stall, it is tied up.
- Dependence. Your outcome depends on the developer’s execution, pricing and financial health.
- Liability to buyers. Under RERA you may be a promoter, with duties to every buyer. The next section explains when.
Your position under RERA VERIFIED
If you take a share of the units or the sales. Under RERA, a landowner who shares in a project’s revenue or area can be a promoter. The Act says that where the person who builds and the person who sells are different, both are promoters and are jointly liable for the Act’s functions and responsibilities.7 MahaRERA’s Circular 12/2017 treats landowners with an area or revenue share as promoters, jointly liable with the developer for the Act’s duties. They are named at registration, their agreement with the developer is published, and their liabilities are tied to that agreement.8 In 2024 a single judge of the Bombay High Court held a JDA partner registered as a promoter liable to refund a buyer with interest, although only its partner had sold the flat and received the money.9 In November 2026 a Division Bench of the same court, in a case about a replacement developer, treated that ruling as one about a promoter’s liability to the buyers of its co-promoter, and distinguished it on the facts. It did not decide whether the landowner in that case, a trust that disputed its registration as co-promoter, was liable to the first developer’s buyers.10 Outside Maharashtra, the Kerala High Court has looked at the landowner’s actual role. It held that landowners who took flats as a fixed consideration, with no role in development and no share in profit or loss, did not have to register the project as promoters, but were to be treated as promoters when executing the buyers’ sale deeds.11 Our guide Is the landowner a promoter under RERA? covers this in detail.
If you sign a development-management contract. In this model you own and fund the project, and the units are sold on your behalf, so you are likely to be a promoter yourself. The Act’s definition covers anyone who “constructs or causes to be constructed” a building of apartments, or develops land into plots, for sale.7 If you are a promoter, the Act’s duties to buyers apply to you, whatever the contract says about who does the work. The developer may be treated as a promoter too: the definition also covers anyone who acts as a builder or developer, and where the builder and the seller are different, both are promoters.7 The contract sets how the developer is paid. Ask how its fee is calculated, whether it depends on sales, what it is owed if sales stall, and whether it bears any of the losses.
Whatever the structure, do not assume that your agreement with the developer limits what buyers can claim from you. In Maharashtra, the Bombay High Court has held that the way a joint development agreement divides the flats does not excuse a registered promoter.9 Take advice from a property lawyer in your state before you sign.
Questions to ask an asset-light developer
- Which model are you offering, exactly: area share, revenue share, DM or a hybrid?
- Under this structure, will I be named as a promoter in the RERA registration?
- What do you bring that I cannot hire separately, and what does it cost me?
- Under DM: how is your fee calculated, and what is it owed on if sales stall?
- Under DM: will you be registered with RERA as a promoter, or as an agent, for this project?
- What happens if approvals are refused or delayed?
- Show me your RERA record: original and actual completion dates, extensions and complaints.
- Can I speak to two landowners you have partnered with?
- Who funds construction, and what security do I have if the money runs out?
Then use our due-diligence checklist on every developer you are considering, including ones that are clients of ours.
- Arvind SmartSpaces, Annual Report 2023-24, page 30 (reasons for joint developments; portfolio mix), Arvind SmartSpaces. Accessed 27 Nov 2026.
- Godrej Properties partners landowner for housing project (PTI, citing the company's regulatory filing, 23 Feb 2026) (secondary), Outlook Business. Accessed 27 Nov 2026.
- Arvind SmartSpaces, Annual Report 2023-24, page 29 (joint development and development-management projects), Arvind SmartSpaces. Accessed 27 Nov 2026.
- Puravankara enters joint development in Bengaluru (Angel One news report of the company's announcement, 9 Mar 2026) (secondary; headline shortened), Angel One. Accessed 27 Nov 2026.
- Della Townships India, website home page and FAQ (company-stated; not linked because the page carries marketing claims), Della Townships India. Accessed 27 Nov 2026.
- MahaRERA registered-project search, project names 'Della' and 'Della Townships', searched 27 Nov 2026, MahaRERA. Accessed 27 Nov 2026.
- Real Estate (Regulation and Development) Act 2016, s.2(zk) and Explanation (unofficial copy of the Act text, as reproduced by Haryana RERA), Haryana RERA, Acts page. Accessed 27 Nov 2026.
- MahaRERA Circular No. 12/2017 (4 Dec 2017), MahaRERA. Accessed 27 Nov 2026.
- Wadhwa Group Housing Pvt Ltd v. Vijay Choksi, Bombay High Court, Second Appeal (St) 21842/2023, 26 Feb 2024, LiveLaw (judgment PDF). Accessed 27 Nov 2026.
- H. Rishabraj Developers v. State of Maharashtra, Bombay High Court (Division Bench), WP 894/2024 with WP 7618/2022, 5 Nov 2026, Indian Kanoon (judgment). Accessed 27 Nov 2026.
- Pooja Constructions v. Secretary, Kerala Uranma Devaswom Board, Kerala High Court, MSA 16/2024, 30 Aug 2024, Indian Kanoon (judgment). Accessed 27 Nov 2026.
This guide explains how these structures generally work. It is not legal or tax advice for your situation. Report an error · Editorial policy