How a township is masterplanned: who does what, in what order

The masterplan is the document every later approval, phase and sale depends on. Here is who prepares it, which rules shape it and the order the work follows, with Maharashtra's township rules as the worked example.

Publisher's note: Optimizer360, which publishes The Township Edit, works with Della Townships. How we keep coverage fair

Overhead view of a hand-coloured township masterplan on a studio table, with tracing paper, a scale ruler, pencils and a cup of tea
AI-generated image. It does not show a real project.
The short answer

A township is masterplanned after the land and the development deal are secured, and before any building is approved or sold. A team of specialists led by an architect or town planner prepares the master layout; surveyors, engineers and accredited environmental consultants supply the studies behind it. In Maharashtra, an integrated township then needs the State's locational clearance, the Collector's letter of intent, approval of the master layout and environmental clearance before work starts. Each phase gets its own building permission and must be registered separately with the state RERA authority before it is marketed. Other states set their own rules.

A township is masterplanned after the land and the development deal are secured, and before any building is approved or sold. The masterplan, called the master layout plan in Maharashtra’s rules, fixes where the roads, open spaces, schools, utilities and homes go, and in what order they are built. Every later approval, phase and RERA registration refers back to it.

This guide uses Maharashtra’s integrated township rules as the worked example, because they spell out who prepares and signs what. They apply across most of the state, but not in Greater Mumbai, MIDC, NAINA and Jawaharlal Nehru Port Trust areas, hill-station municipal councils, the Lonavala Municipal Council area, eco-sensitive regions notified by the Union environment ministry and some other areas.1 Other states have their own township rules and thresholds. Ask a town planner which rules apply to your land.

The sequence at a glance

  1. Land and the deal. Title, ownership and development rights over every parcel.
  2. Site studies. Survey, contours, plan zoning and the land that cannot be built on.
  3. State clearance. In Maharashtra, the State's locational clearance and the Collector's letter of intent.
  4. Master layout plan. Prepared by a specialist team and approved by the Collector or the planning authority.
  5. Environmental clearance. Needed before any construction or land preparation starts.
  6. Phasing, building permissions and RERA. Each phase is approved, registered and sold on its own.
  7. Build, occupy and hand over. Infrastructure is maintained by the developer until it is handed to a local body.

Who does what VERIFIED

The table lists the main roles and where Maharashtra’s rules, the national environmental rules and RERA bring them in.

Who What they do Where the rules come in
Landowners Prove title for every parcel; sign and register the development agreement or power of attorney UDCPR 14.1.1.3 and 14.1.1.4(i)1
Developer (the “project proponent”) Applies for every clearance; pays the premiums; gives a bank guarantee for basic infrastructure; builds and maintains the infrastructure until handover UDCPR 14.1.1.4 to 14.1.1.7, 14.1.1.10 and 14.1.1.1212
Masterplanning team Prepare and sign the master layout plan: experts in each field, in a team headed by an architect or town planner registered with the Institute of Town Planners, India (ITPI). The owner or developer also signs. Urban design concept plans go with the master plan UDCPR 14.1.1.6(i)(h) and 14.1.1.10(iv)(l)1
Surveyors Prepare the contour map; the surveying agency certifies that it is accurate UDCPR 14.1.1.6(i)(i)1
Architect Certifies the estimated cost of basic infrastructure, which sets the bank guarantee. The developer reports through the architect when work reaches plinth level, and since March 2024 that work is certified by the architect, a licensed engineer or a supervisor UDCPR 14.1.1.12(vi) and 14.1.1.6(vi)(b)12
Engineers Design to the standards the rules set for the developer: roads to Indian Road Congress standards, water supply, drainage, sewage and solid-waste systems, power and the fire station UDCPR 14.1.1.7(iii)(h), 14.1.1.10(v) and 14.1.1.12(vii)1
Environmental consultant Prepares the environmental impact assessment report; must be accredited with QCI/NABET or another agency the ministry notifies EIA Notification 2006, para 134
Authorities State Government, Collector or planning authority, Town Planning offices, the State Environment Impact Assessment Authority and the state RERA authority (see the steps below) UDCPR 14.1; EIA Notification 2006, para 2; RERA s.3146

Step 1: the land and the deal come first

Planning starts with ownership, not drawings. Under Maharashtra’s township rules the developer must own every parcel, and ownership includes rights under registered development agreements or powers of attorney. The application to the State must carry the 7/12 extracts or property cards and copies of those registered agreements.1 So a landowner’s agreement with the developer is signed and registered before the masterplan is approved, not after.

Our guide on how to develop 100 acres sets out title, zoning and conversion, and the records each owner will need. If you take a share of the project’s area or revenue, you may also be treated as a promoter under RERA.6 See whether the landowner is a promoter.

Step 2: site studies

The masterplanners need to know what the land allows before they draw anything. Maharashtra’s rules set out the main inputs:12

  • Size and shape. At least 40 hectares (about 100 acres; our land-unit converter does the arithmetic), in one contiguous piece. Land split by a road, canal or pipeline still counts if the developer builds the connecting roads or bridges.
  • Access. An 18-metre access road. A proposed road can serve for the early clearances if a 12-metre road exists, but the 18-metre access must exist before commencement certificates cover more than 25% of the project’s FSI.
  • Land that cannot be built on. No construction within the flood line, in hill-top and hill-slope zones, or on slopes of 1:5 or steeper. Hill slopes, flood zones and eco-sensitive buffers together can be at most 40% of the township.
  • Land that cannot be included. Notified forests, water bodies, mangroves, national parks, defence land and several other categories.
  • Maps. The regional or development plan, village maps, a certified contour map and a satellite or drone image.

Step 3: what the master layout plan and the township must provide VERIFIED

A township masterplan is not just a site layout. In Maharashtra the master layout plan must set aside land and built space for town-level amenities, with minimums for each, and the developer must meet set standards for roads, utilities, trees and green ratings.1 The March 2024 changes revised some of these tables, including the space for economic activities, so ask your planner for the current figures.2

  • Open space: gardens and parks, playgrounds, and a further 10% open space in each sector-level layout.
  • Social and economic uses: schools, health care, markets, a town hall or auditorium, and space for offices, shops, hotels, IT and other non-polluting uses.
  • Public utilities: a fire station, sewage and solid-waste plants, a bus station, a police station and an electric sub-station, with exceptions where some already exist nearby.
  • Social housing: at least 15% of the residential basic FSI as homes for economically weaker and lower-income groups.
  • Movement: a road pattern linked to the roads outside, an 18-metre right of way for main roads, footpaths at least 2 metres wide on roads 12 metres or wider, and a cycle track at least 3 metres wide across the township.
  • Resources: rainwater harvesting and recycled water, no groundwater as the source of supply, treatment of all sewage and solid waste on site, and at least 10% of the power for common infrastructure from renewable sources.
  • Trees and green rating: at least 150 indigenous trees per hectare, and buildings rated at least 3-star GRIHA or, since March 2024, Silver IGBC or LEED or an equivalent ASSOCHAM GEM rating.12
  • A phased programme for building the physical infrastructure and amenities, with costs.1

That last item matters most to buyers: it decides which roads, schools and utilities exist when the first residents move in.

Step 4: approvals, in order VERIFIED

For a Maharashtra integrated township, the regulation sets this sequence and these deadlines for the authorities:12

  1. Locational clearance. The State Government decides within 90 days, after consulting a High Power Committee chaired by the Urban Development Department’s Principal Secretary (added in March 2024; the 2020 text named the Director of Town Planning). Since March 2024 the application must include an area statement, showing the land under hill slopes and other constraints, plan reservations, and the plot and built-up areas for each mandatory town-level amenity. So the outline of the masterplan has to exist at this stage.
  2. Letter of intent. The Collector issues it within 45 days, for at least 40 hectares at first, after checking that the developer holds ownership and development rights in all the land.
  3. Master layout plan. The Collector, or the planning authority where one has jurisdiction, sends it to the Divisional Joint Director of Town Planning, who has two months to give technical remarks. The decision follows within a month. Approval comes with a condition: no work may start without environmental clearance.
  4. Building permission. Granted for buildings under the approved master layout within 30 days. The application must include the environmental clearance.

Our guide to Maharashtra’s integrated township rules explains each stage. Ask the Town Planning office whether it is applying the 2020 text or the text as changed in March 2024.

Step 5: environmental clearance VERIFIED

Under the EIA Notification 2006, as its entry for buildings and townships was rewritten in January 2025, townships and area development projects covering 50 hectares or more, or with 1,50,000 m² or more of built-up area, need an environmental impact assessment report and are appraised as Category B1 projects. Building projects of 20,000 m² or more of built-up area need environmental clearance too.3 In August 2025 the Supreme Court upheld that notification, except for an exemption for industrial sheds and educational buildings, which it struck down. The township thresholds did not change.5

The notification shapes the timing of the masterplan in four ways:4

  • Timing. Clearance is needed before any construction work or preparation of land starts, apart from securing the land.
  • Who decides. Category B projects are decided at state level, normally by the State Environment Impact Assessment Authority on the advice of the State Expert Appraisal Committee.
  • What is filed. For townships and building projects, a conceptual plan goes with the application forms in place of a pre-feasibility report.
  • No public hearing. Townships and area development projects are exempt from the public-consultation stage, unless they contain a Category A project or activity.

A 100-acre holding is about 40.5 hectares, below the 50-hectare mark, so its built-up area decides which entry applies. Ask your environmental consultant how the project, and each phase of it, will be appraised.

Step 6: phasing, RERA and handover VERIFIED

A large township is built in phases. Maharashtra’s rules let the basic infrastructure and amenities be completed for the whole project or phase by phase. Before a partial occupancy certificate is issued, the infrastructure due under the phased programme must be complete. The township must be completed within 10 years of master plan approval, unless the Government allows longer.12

RERA then treats each phase as a separate project. No plot, flat or villa in a phase may be advertised, booked or sold until that phase is registered with the state RERA authority. The application must include the approvals and commencement certificate for the phase, and the sanctioned plan, layout plan and specifications of the phase and of the whole project. It must also set out the plan of development works and facilities, including fire-fighting, drinking water and the use of renewable energy.6

Once buyers in a phase have booked, that phase’s plans become harder to change. The developer must complete the phase to its sanctioned plans, layout plans and specifications. After those plans have been disclosed to buyers who agree to take a unit, the developer cannot change a buyer’s own unit without that buyer’s consent. The exceptions are minor changes the buyer asks for, and minor changes needed for architectural or structural reasons that an authorised architect or engineer recommends and verifies, after proper declaration and intimation to the buyer. Any other change to the sanctioned plans, layout plans or specifications of the buildings or common areas within the project needs the prior written consent of at least two-thirds of the allottees who have agreed to take apartments in that building, not counting the promoter. A buyer with several units counts as one allottee.6 Because RERA treats each phase as a separate project, these rules are written for the phase. Ask a lawyer how they apply to changes elsewhere in the township’s master layout. Our step-by-step guide to checking a project on RERA shows where to read a phase’s registration and documents.

Handover comes last. In Maharashtra the developer maintains the roads, street lights, water supply and drainage until the project is complete, and may collect contributions or a corpus from buyers for it. It then hands the infrastructure, with any unspent corpus, to the local body. The regulation also provides for a local authority to be formed for the township.1 Our explainer on what an integrated township is covers what this means for residents.

How developers organise the design work

Beyond who signs the master layout, the rules above do not say how a developer must organise its design team, and developers describe their approaches differently. The examples below come from the companies’ own public material.

Della Townships describes what it calls multidisciplinary masterplanning, which brings disciplines including urban design, architecture, hospitality, landscape, wellness, mobility, engineering and operations into one integrated process. It says this is led through Jimmy Mistry Design Studios, and that it offers an end-to-end service from concept to operations (company-stated, as of 27 November 2026).7 DEVELOPER-STATED When we searched MahaRERA’s register by project name on 27 November 2026, none of the township collaborations Della Townships lists in Maharashtra appeared.8 We have not searched other states’ registers. We name none of the collaborations.

We found less recent public material from other developers on how they organise masterplanning. In the sources we checked:

  • Mahindra Lifespaces said in January 2025 that it had over 5,000 acres of ongoing and forthcoming projects under development or management at its integrated developments and industrial clusters, across four locations.9 Mahindra Group releases from 2007 say the group brought in international firms to plan two of its developments: a residential township “master planned by HOK International”, to be developed in four phases, each self-contained, and an integrated business city, set up as a special economic zone, whose master plan was “developed by M/s Jurong, Singapore”.1011
  • Arvind SmartSpaces’ 2023-24 annual report says its “competence lies in designing three distinct project types: short-term, medium-term, and long-term”. It also describes townships taken up under joint development and development-management models.12

These examples are illustrative, not a ranking. A description of a design process says nothing on its own about delivery: judge each developer on its approvals, its RERA records and the projects it has completed. Our developer profiles collect the public records we have checked. Some developers add a theme or a wellness focus on top of the masterplan. Our guide to wellness townships explains how to tell substance from marketing.

Questions to ask about any township masterplan
  • Who prepared and signed the master layout plan? Who headed the team, and what professional registration do they hold? (The regulation asks for a team ‘headed by an Architect or Town Planner registered with Institute of Town Planners India (ITPI)’.)
  • Has the master layout been approved? By which authority, and on what date? Was it approved under the 2020 text or the March 2024 changes?
  • What does the phased programme promise, and which roads, utilities, schools and open spaces come with the first phase?
  • Has environmental clearance been granted? Under which entry, and by which authority?
  • Is the phase you are looking at registered with RERA? Do the registration documents include the layout of the whole project?
  • Who maintains the roads, water and drainage until handover, and how is the maintenance corpus held?
  • Landowners: will you be named as a promoter? Who pays the premiums and the bank guarantee, and what happens to your share if a phase is delayed?

Each of these answers is on paper somewhere: in the approvals, the environmental clearance or the RERA registration. Ask to see the document, not a summary of it.

Sources
  1. Unified Development Control and Promotion Regulations (UDCPR) 2020: title page (applicability) and Regulation 14.1 (Integrated Township Project), text as sanctioned 2 Dec 2020, incl. 14.1.1.2 to 14.1.1.7, 14.1.1.10 to 14.1.1.12 and 14.1.2 (for the changes directed on 5 Mar 2024, see source 2), Urban Development Department, Government of Maharashtra (copy hosted by GRIHA; mirror). Accessed 27 Nov 2026.
  2. Notice No. TPS-1821/452/CR-105/2022/UD-13, 5 Mar 2024, under ss.37(1AA)(a) and 20(3) of the MRTP Act 1966, proposing changes to UDCPR Regulation 14.1 (Integrated Township Project), with directions under s.154(1) that they come into force immediately; Schedule A of changes (scanned image; English pp.5–18), Urban Development Department, Government of Maharashtra. Accessed 27 Nov 2026.
  3. MoEFCC Notification S.O. 523(E), 29 Jan 2025, substituting item 8 of the Schedule to the EIA Notification 2006, Gazette of India Extraordinary Part II s.3(ii), PARIVESH, Ministry of Environment, Forest and Climate Change (Gazette copy). Accessed 27 Nov 2026.
  4. EIA Notification 2006 (S.O. 1533(E)) and subsequent amendments, compilation up to March 2025; it does not include later amendments: paras 2, 6, 7(i) (Stage 1 screening; Stage 3 public consultation, exception (d)) and 13, and Appendix V para 3 (unofficial consolidated copy; the Gazette notifications prevail), Tamil Nadu Pollution Control Board (copy of MoEFCC compilation). Accessed 27 Nov 2026.
  5. Vanashakti v. Union of India, Supreme Court of India, W.P.(C) 166 of 2025, 2025 INSC 961, 5 Aug 2025 (paras 19, 24, 46–47) (judgment text, mirror), CaseMine. Accessed 27 Nov 2026.
  6. Real Estate (Regulation and Development) Act 2016, ss.2(zk) (Explanation), 3 (with Explanation), 4(2)(c)–(e) and 14(1)–(2) (with Explanation) (statute text, unofficial copy), Haryana RERA, Acts page. Accessed 27 Nov 2026.
  7. Della Townships India, website home page ('Multidisciplinary Masterplanning' section) and FAQ 18 (company-stated; not linked because the page carries marketing claims), Della Townships India. Accessed 27 Nov 2026.
  8. MahaRERA registered-project search, project names 'Della' and 'Della Townships', searched 27 Nov 2026, MahaRERA. Accessed 27 Nov 2026.
  9. Mahindra Lifespaces press release on nine-month FY25 results (31 Jan 2025), 'About Mahindra Lifespace Developers' paragraph (company-stated), Mahindra Group. Accessed 27 Nov 2026.
  10. Mahindra Group press release, 15 May 2007: a residential township 'master planned by HOK International', to be developed in four self-contained phases (company-stated) (not linked: the release names the development), Mahindra Group. Accessed 27 Nov 2026.
  11. Mahindra Group press release, 2 Mar 2007: master plan of an integrated business city 'developed by M/s Jurong, Singapore' (company-stated) (not linked: the release names the development), Mahindra Group. Accessed 27 Nov 2026.
  12. Arvind SmartSpaces, Annual Report 2023-24, p.29 (company-stated), Arvind SmartSpaces. Accessed 27 Nov 2026.

This guide explains how these structures generally work. It is not legal or tax advice for your situation. Report an error · Editorial policy